AUGUST 27, 2024:
Construction will continue for the next few weeks in various locations around town. The intersection of Main Avenue and 12th Street at the entrance to Cummings Field will likely be closed a few times over the course of the project, please watch for signage directing to alternate routes. The Highway 1 project should be wrapping up concrete this week and will tentatively begin milling the asphalt next week.
AUGUST 15, 2024:
Phase two of the City Street project and the Highway 1 project will both start on Monday August 19th. The Highway 1 project will start off with curb and gutter, ADA ramp and sidewalk work. The City project will include patching areas in the previously worked on intersections and various areas of milling and overlay throughout town. (Blue areas on the map) Burlwood will be completely reconstructed; the City and Contractor will work with residents in that neighborhood on timing and access to properties. Next week will be very busy with not only construction work but school starting as well, we ask everyone to be careful and cautious when driving, biking and walking around town.
JUNE 25, 2024:
The majority of concrete work has been completed. Workers will be in town later this week to crack seal areas of North 14th Street and 87th St SE. Also, late this week or early next week a seeding crew will begin to reseed grass in the areas dug up behind replaced curbs. We will have most of the month of July off from construction work and asphalt crews will show up in early August. Please let us know if you notice any issues in the completed areas.
MAY 28, 2024:
Construction has started on Fir Avenue. This first crew will be doing curb and gutter, driveway and valley gutter areas (mostly the areas in red on the map). They will continue working South from Fir Avenue, timing is hard to pinpoint as it will depend on how much work can be done each day. Some residents may have to park on the street temporarily if their driveway is impacted. The contractors have been going door to door to notify residents in the work area, if you have any questions or concerns you can ask them directly or call City Hall. If you have sprinklers in your yard near the curb it would be helpful if you could mark their locations to alert the contractors.
UPDATE MAY 24, 2024:
You may have already seen construction workers around town, but the 2024 Street Project will officially begin on Tuesday May 28th. Once the contractor is in town and setup they will make their plan for timing and locations. As soon as we know this information we will pass it on.